[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129845":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129845,794,1,"单选题","围堰拆除应制定专项方案。且应在围堰内土建工程、机电设备安装工程通过（ ）后进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专项检验",false,{"key":16,"text":17,"correct":18},"B","专项验收",true,{"key":20,"text":21,"correct":14},"C","专项检测",{"key":23,"text":24,"correct":14},"D","专项监测","2020版教材页码P385 围堰拆除应制订专项方案，且应在围堰内土建工程、机电设备安装工程通过专项验收后进行。主围堰拆除时严禁发生水体自流通过全闸的通闸现象。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]