[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129833":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1129833,794,1,"单选题","《水运建设市场监督管理办法》第十九条规定（ ）应当按照合理工期组织项目实施，不得任意压缩合理工期和无故延长工期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目单位",true,{"key":16,"text":17,"correct":18},"B","施工单位",false,{"key":20,"text":21,"correct":18},"C","管理单位",{"key":23,"text":24,"correct":18},"D","监理单位","2020版教材页码P373-P376 项目单位应当按照合理工期组织项目实施，不得任意压缩合理工期和无故延长工期，并应当按照合同约定支付款项;不得明示或者暗示施工单位使用不合格的材料、黑钻压卷，金考典软件考前一周更新，下载链接 www.jinkaodian.com 构配件和设备;项目单位按照合同约定自行采购材料、构配件和设备的，应当保证其满足国家有关标准的规定，符合设计文件要求。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]