[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129818":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129818,794,1,"单选题","采用爆破排淤填石法改良地基，在确定一次爆破药量时，应按要求进行（ ），当不能满足时，可采用多段微差爆破工艺减少一次爆破药量，或采取气幕防护措施降低爆破地震波与冲击波对建筑物的影响。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","作业距离核算",false,{"key":16,"text":17,"correct":14},"B","运输距离核算",{"key":19,"text":20,"correct":21},"C","安全距离核算",true,{"key":23,"text":24,"correct":14},"D","推进距离核算","2020版教材页码P88-P91 爆破排淤填石法：一次推进距离与堤身断面方量、淤泥厚度及抛填施工能力有关，一般为5 -7m ，最大不超过9m 。在确定一次爆炸药量时应按要求进行安全距离核算，当不能满足时可采用多段微差爆破工艺，减少一次爆炸药量，或采取气幕防护措施降低爆炸地震波与冲击对建筑物的影响。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]