[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129805":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129805,794,1,"单选题","采用RTK平面控制测量时，基准站应架设在（ ）上，且基准站周边环境应满足相应的要求，有条件时应架高。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","测量点",false,{"key":16,"text":17,"correct":18},"B","控制点",true,{"key":20,"text":21,"correct":14},"C","位移点",{"key":23,"text":24,"correct":14},"D","沉降点","2020版教材页码P103-P105 RTK平面控制测量基准站架设规定 1. 基准站应架设于控制点上，且该点应具有相当于四等水准及以上精度的高程。 2. 基准站周边环境应满足相应的要求。 3. 数据链天线架设高度应满足基准站与流动站间差分数据传输的要求，有条件时，应架高。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]