[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129800":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1129800,794,1,"单选题","对混凝土温度的监测频次，在升温期间，环境温度、冷却水温度和内部温度应每（ ）监测一次。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2～4h",true,{"key":16,"text":17,"correct":18},"B","4～6h",false,{"key":20,"text":21,"correct":18},"C","6～8h",{"key":23,"text":24,"correct":18},"D","8～12h","2020版教材页码P59-P66 混凝土温度和应变监测频次应符合下列规定: （1）混凝土浇筑温度检测每台班不应少于2次。 （2）升温期间，环境温度、冷却水温度和内部温度应每2 - 4h监测一次，降温期间应每天监测2-4次。 （3）温度监测持续时间不应少于20d ，应变监测不应少于60d 。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]