[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129775":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129775,794,1,"单选题","人工降低地下水位的方法是（ ）临时防渗措施。该法可以降低水头，或使地下水位降至渗透变形土层以下。在弱透水层中采用轻型井点、喷射井点；在较强的透水层中采用深井法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","很少使用的",false,{"key":16,"text":17,"correct":18},"B","最常见的",true,{"key":20,"text":21,"correct":14},"C","一般不使用的",{"key":23,"text":24,"correct":14},"D","唯一使用的","2020版教材页码P93-P95 人工降低地下水位：该方法是最常见的临时防渗措施，在施工期处理管涌、流沙（土）时也常采取这一最简单易行的办法。该法可以降低水头，或使地下水位降至渗透变形土层以下。在弱透水层中采用轻型井点、喷射井点;在较强的透水层中采用深井法。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]