[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129768":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1129768,794,1,"单选题","深层搅拌桩法壁状加固时，相邻桩的施工时间间隔不宜超过（ ）h。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","12",true,{"key":16,"text":17,"correct":18},"B","24",false,{"key":20,"text":21,"correct":18},"C","6",{"key":23,"text":24,"correct":18},"D","36","2020版教材页码P85-P88 壁桩加固时，相邻桩的施工间隔不宜超过12h。如间隔时间太长，与相邻桩无法搭接时，应采取局部补桩或注浆等补强措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]