[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129763":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1129763,794,1,"单选题","为减少预应力筋松弛的影响，从零应力开始，张拉至（ ）倍预应力筋的张拉控制应力σcon。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1．03",true,{"key":16,"text":17,"correct":18},"B","1．05",false,{"key":20,"text":21,"correct":18},"C","1．08",{"key":23,"text":24,"correct":18},"D","1．10","2020版教材页码P69-P71 从零应力开始，张拉至1.03倍预应力筋的张拉控制应力σcon",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]