[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129723":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1129723,794,1,"单选题","板桩建筑物沉桩施工中，下沉的板桩将邻近已沉的板桩“上浮”时，对“上浮”的板桩，应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","复打至设计标高",true,{"key":16,"text":17,"correct":18},"B","在后续施工工序中予以调整",false,{"key":20,"text":21,"correct":18},"C","按此桩顶标高进行控制",{"key":23,"text":24,"correct":18},"D","重新确定后沉板桩的桩顶标高","2020版教材页码P138-P139 下沉的板桩将邻近己沉的板桩\"带下\"或\"上浮\"时可根据\"带下\"的情况重新确定后沉板桩的桩顶标高，对\"上浮\"的板桩，应复打至设计标高。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]