[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129712":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1129712,794,1,"单选题","关于一般的板桩码头施工的说法，正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","导向梁距板桩墙顶的距离应小于替打套入桩的长度",false,{"key":16,"text":17,"correct":14},"B","拉杆连接铰的转动轴线应位于垂直面上",{"key":19,"text":20,"correct":14},"C","锚碇板（墙）的设置高程应尽量放高，以提高其承载力",{"key":22,"text":23,"correct":24},"D","沉桩应以桩尖设计标高作为控制标准",true,"2020版教材页码P138-P139 沉桩应以桩尖设计标高作为控制标准。当桩尖沉至设计标高有困难时，应会同设计单位研究处理。当有承载力要求时，要求沉桩双控。沉桩的允许偏差应符合现行行业标准的有关规定。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]