[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129708":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129708,794,1,"单选题","重力式码头基床抛石前，要对基槽回淤沉积物进行检查，重力密度大于（）kN／m3的回淤沉积物厚度不应大于300mm，超过时用泥泵清淤。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":18},"B","12．6",true,{"key":20,"text":21,"correct":14},"C","13",{"key":23,"text":24,"correct":14},"D","13．6","2020版教材页码P114-P118 抛石前要对基槽断面尺寸、标高及回淤沉积物进行检查，重力密度大于12.6kN\u002Fm3的回淤沉积物厚度不应大于300mm ，超过时用泥泵清淤。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]