[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129676":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129676,794,1,"单选题","斜坡堤水下土工织物铺设后应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","及时抛（回）填，以便下道工序施工",false,{"key":16,"text":17,"correct":18},"B","及时抛（回）填，防止风浪损坏",true,{"key":20,"text":21,"correct":14},"C","裸露一段时间，以便施工检查",{"key":23,"text":24,"correct":14},"D","裸露一段时间，以便下道工序施工","2020版教材页码P142-P143 水下土工织物铺设后应及时抛（回）填，压载稳定防止风浪损坏;陆上土工织物铺设后，应及时覆盖，防止日晒老化。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]