[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129671":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1129671,794,1,"单选题","对高桩码头上部装配式整体结构的混凝土施工，正确的做法是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应将纵横梁节点、预制板缝及码头面层的混凝土一次浇筑",false,{"key":16,"text":17,"correct":14},"B","应先浇筑横梁节点的混凝土，然后将纵梁、预制板缝及码头面层一次浇筑",{"key":19,"text":20,"correct":14},"C","应先浇筑纵横梁节点的混凝土，然后将预制板缝及码头面层一次浇筑",{"key":22,"text":23,"correct":24},"D","应先浇筑纵横梁节点及预制板缝中的混凝土，再浇筑码头面层",true,"2020版教材页码P134 现场浇筑大面积码头面层混凝土时，应特别注意防雨、防裂和加强养护等。装配式整体结构应先浇筑纵横梁节点及预制板缝中的混凝土，再浇筑码头面层。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]