[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129670":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1129670,794,1,"单选题","高桩码头叠合板预制件在安装就位以后，要（ ），以使构件稳固。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","用张紧器临时拉条稳住",false,{"key":16,"text":17,"correct":14},"B","将两根相接的底部伸出的钢筋焊接起来",{"key":19,"text":20,"correct":14},"C","立即浇筑混凝土",{"key":22,"text":23,"correct":24},"D","将接缝处伸出的钢筋焊接起来",true,"2020版教材页码P131-P133 叠合板在安装就位以后，要将接缝处伸出的钢筋焊接起来。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]