[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1129653,794,1,"单选题","水运工程混凝土和砂浆材料用量定额中，计算1m3混凝土及砂浆材料用量时（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可以直接套用",true,{"key":16,"text":17,"correct":18},"B","尚应考虑施工中倒运的损失量",false,{"key":20,"text":21,"correct":18},"C","尚应考虑混凝土运输中的损失量",{"key":23,"text":24,"correct":18},"D","尚应考虑砂、石筛洗中的耗损量","本定额为1m3混凝土及砂浆体积的材料用量，定额已包括了材料在施工中的工地小搬运和操作损耗，以及砂、石筛洗的损耗，砂用量已考虑了自然条件下含水增加的体积，使用时无论砂和碎石的实际密度及实际含水率多少，均不作调整。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]