[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129649":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129649,794,1,"单选题","沿海水工工程在编制概算时需在套用《沿海港口水工建筑工程定额》计算出定额直接费、基价定额直接费后加乘扩大系数，直立式防波堤取（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1．01～1．03",false,{"key":16,"text":17,"correct":14},"B","1．02～1．04",{"key":19,"text":20,"correct":21},"C","1．02～1．05",true,{"key":23,"text":24,"correct":14},"D","1．03～1．05","编制预算时，可根据各章的有关规定直接使用本定额;编制概算时，需在套用本定额计算出定额直接费、基价定额直接费后加乘扩大系数:码头、直立式防波堤、直立式护岸等工程1.02-1.05;枝引桥、斜坡式引堤、斜坡式防波堤、斜坡式护岸等工程1.01-1.03。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]