[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129607,794,1,"单选题","项目进度控制机构应以（ ）为责任主体。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目总工程师",false,{"key":16,"text":17,"correct":14},"B","分管进度计划的项目副经理",{"key":19,"text":20,"correct":21},"C","项目经理",true,{"key":23,"text":24,"correct":14},"D","子项目负责人","为保证实施项目进度控制，应建立以项目经理为责任主体，有各子项目负责人、计划人员、调度人员、作业队长及班组长参加的项目进度控制体系。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]