[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129603":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1129603,794,1,"单选题","使用国外贷款的建设项目，应依据规定分别编制人民币和外币概算。其中：施工取费的计算，以（ ）为取费基础。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","直接工程费",false,{"key":16,"text":17,"correct":14},"B","定额直接费",{"key":19,"text":20,"correct":14},"C","直接费",{"key":22,"text":23,"correct":24},"D","基价定额直接费",true,"使用国外贷款的建设项目，应依据本规定分别编制内币和外币概算。其中:（1）施工取费的计算，以基价定额直接费为取费基础。 （2）计算总概算第二部分的有关费用时，进口设备和材料应按其到岸价格（CIF）乘以当时的外汇牌价折算成人民币后，按照本规定有关费率计算。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]