[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129547":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1129547,794,1,"单选题","投标人在投标截止时间之前撤回已提交投标文件的，招标人应当自收到投标人书面撤回通知之日起（ ）日内退还已收取的投标保证金。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",true,{"key":16,"text":17,"correct":18},"B","7",false,{"key":20,"text":21,"correct":18},"C","10",{"key":23,"text":24,"correct":18},"D","15","投标人在投标截止时间之前撤回已提交投标文件的，招标人应当自收到投标人书面撤回通知之日起5日内退还已收取的投标保证金。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]