[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129488":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129488,794,1,"单选题","码头接岸结构及岸坡在施工期和使用期整体稳定性验算应符合下列规定：可冲刷河段或海岸建造高桩码头尚应考虑（ ）对岸坡稳定的影响。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","水位上升",false,{"key":16,"text":17,"correct":14},"B","水位骤降",{"key":19,"text":20,"correct":21},"C","冲刷",true,{"key":23,"text":24,"correct":14},"D","雨期","",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]