[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129292":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129292,794,1,"单选题","重力式码头预制沉箱的接高，采取（ ）接高，所需费用高，一般适用于所需接高沉箱数量多、风浪大、地基条件好和水深适当的情况。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","漂浮",false,{"key":16,"text":17,"correct":18},"B","座底",true,{"key":20,"text":21,"correct":14},"C","半潜",{"key":23,"text":24,"correct":14},"D","固定","座底接高需建抛石基床，所需费用高，一般适用于所需接高沉箱数量多、风浪大、地基条件好和水深适当的情况。漂浮接高需抛锚，缆绳系住沉箱占用水域面积大，受风浪影响大，工作条件差，一般适用于所需接高沉箱数量少、风浪小和水深较大的情况。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]