[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129269":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129269,794,1,"单选题","高桩码头沉桩后对岸坡进行回填或抛石施工前，如遇异常情况，如大风暴、特大潮等过后，必须（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","加速抛填施工",false,{"key":16,"text":17,"correct":18},"B","及时施测回淤，必要时再次清淤",true,{"key":20,"text":21,"correct":14},"C","进行夹桩",{"key":23,"text":24,"correct":14},"D","作好施工记录","",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]