[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129258":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1129258,794,1,"单选题","高桩码头预制构件存放按三点以上受力状态设计的预制构件，宜采用（ ）支垫存放。垫木应均匀铺设，并应注意场地不均匀沉降对构件的影响。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","两点",false,{"key":16,"text":17,"correct":14},"B","五点",{"key":19,"text":20,"correct":14},"C","三点",{"key":22,"text":23,"correct":24},"D","多点",true,"按两点吊设计的预制构件，可用两点支垫存放，但应避免较长时间用两点堆置，致使构件发生挠曲变形。必要时可采用多点垫或其他方式存放。按三点以上设计的预制构件，宜采用多点支垫存放。垫木应均匀铺设，并应注意场地不均匀沉降对构件的影响。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]