[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1129191,794,1,"单选题","高桩码头岸坡回填时，高桩基处的回填应（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","先回填水侧",false,{"key":16,"text":17,"correct":14},"B","先回填陆侧",{"key":19,"text":20,"correct":14},"C","水陆两侧对称回填",{"key":22,"text":23,"correct":24},"D","沿桩周对称回填",true,"",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]