[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129189":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129189,794,1,"单选题","高桩码头在接岸结构岸坡回填土和抛石施工时，采用板桩的锚碇结构前回填时，应按设计要求（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分层自密",false,{"key":16,"text":17,"correct":14},"B","不分层自密",{"key":19,"text":20,"correct":21},"C","分层夯实",true,{"key":23,"text":24,"correct":14},"D","不分层夯实","",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]