[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129187":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129187,794,1,"单选题","高桩码头沉桩后进行岸坡抛填时，应（ ）进行。如设计另有规定，应满足设计要求。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由岸向水域分层",false,{"key":16,"text":17,"correct":18},"B","由水域向岸分层",true,{"key":20,"text":21,"correct":14},"C","由岸向水域",{"key":23,"text":24,"correct":14},"D","由水域向岸","",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]