[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129151":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129151,794,1,"单选题","斜坡堤在软土地基上的抛石时，当堤侧有块石压载层时，应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先抛堤身，后抛压载层",false,{"key":16,"text":17,"correct":18},"B","先抛压载层，后抛堤身",true,{"key":20,"text":21,"correct":14},"C","在低潮时抛压载层",{"key":23,"text":24,"correct":14},"D","在高潮时抛压载层","软土地基上的抛石顺序要求：1.当堤侧有块石压载层时，应先抛压载层，后抛堤身。 2.当有挤淤要求时，应从断面中间逐渐向两侧抛填。 3.当设计有控制抛石加荷速率要求时，应按设计要求设置沉降观测点，控制加荷间歇时间。 4.当在士工织物加筋垫层或软体排上抛石时，应先抛填保护层，再按照有利于拉紧土工织物的顺序进行抛填。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]