[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129149":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129149,794,1,"单选题","高桩码头沉桩后进行回填或抛石时，在基桩处，沿桩周对称抛填，桩两侧高差不得大于（ ）。如设计另有规定，应满足设计要求。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0．5m",false,{"key":16,"text":17,"correct":18},"B","1m",true,{"key":20,"text":21,"correct":14},"C","1．5m",{"key":23,"text":24,"correct":14},"D","2m","抛填时，应由水域向岸分层进行，在基桩处，沿桩周对称抛填，桩两侧高差不得大于4m。如设计另有规定，应满足设计要求。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]