[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128825":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1128825,793,2,"多选题","坝断面范围内必须清除( )，并将清理后的地基表面土层压实",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","地基的草皮",true,{"key":16,"text":17,"correct":14},"B","岸坡上的草皮",{"key":19,"text":20,"correct":14},"C","树根",{"key":22,"text":23,"correct":14},"D","含有植物的表土",{"key":25,"text":26,"correct":27},"E","以上都不正确",false,"ABCD","2021\u002F2020版教材P79页 1）坝断面范围内必须清除地基、岸坡上的草皮、树根、含有植物的表土、蛮石、垃圾及其他废料，并将清理后的地基表面土层压实。",{"id":6,"name":31,"category":32,"favorite":33},"二建水利水电实务","建筑工程",0]