[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128668":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1128668,793,2,"多选题","根据《水利工程施工监理规范》（SL288-2014），水利工程施工实施阶段监理工作的内容中，开工条件的控制涉及（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","签发开工通知",true,{"key":16,"text":17,"correct":14},"B","分部工程开工",{"key":19,"text":20,"correct":21},"C","分项工程开工",false,{"key":23,"text":24,"correct":14},"D","单元工程开工",{"key":26,"text":27,"correct":14},"E","混凝土浇筑开仓","ABDE","水利工程建设项目施工监理实施阶段的开工条件括签发开工通知、分部工程开工、单元工程开工、混凝土浇筑开仓。",{"id":6,"name":31,"category":32,"favorite":33},"二建水利水电实务","建筑工程",0]