[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128614":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1128614,793,2,"多选题","根据《水土保持法》，水土保持方案编制形式包括水土保持方案()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","报告书",true,{"key":16,"text":17,"correct":14},"B","报告表",{"key":19,"text":20,"correct":21},"C","论证报告",false,{"key":23,"text":24,"correct":21},"D","论证书",{"key":26,"text":27,"correct":21},"E","论证表","AB","【考点】《水土保持法》与工程建设有关的规定。 《水土保持法》规定，水土保持方案分为“水土保持方案报告书”和“水土保持方案报告表”。其中，“水土保持方案报告书”是指在山区、丘陵区、风沙区修建铁路、公路、水工程，开办矿山企业、电力企业和其他大中型工业企业，在动工之前向水行政主管部门递交的防治因生产建设活动造成水土流失的措施和工作计划。“水土保持方案报告表”是指在山区、丘陵区、风沙区依照矿产资源法的规定开办乡镇集体矿山企业和个体申请采矿，在动工之前向水行政主管部门递交的以表格形式表述的防治水土流失的措施和工作计划。故本题应选AB。",{"id":6,"name":31,"category":32,"favorite":33},"二建水利水电实务","建筑工程",0]