[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128611":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1128611,793,2,"多选题","（2017年）下列水利水电工程注册建造师签章文件中，属于进度管理文件的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","暂停施工申请表",true,{"key":16,"text":17,"correct":14},"B","复工申请表",{"key":19,"text":20,"correct":21},"C","施工月报",false,{"key":23,"text":24,"correct":14},"D","施工进度计划报审表",{"key":26,"text":27,"correct":21},"E","变更申请表","ABD","考点:二级建造师（水利水电工程）施工管理签章文件目录。进度管理文件包括：施工进度计划报审表、暂停施工申请表、复工申请表、施工进度计划调整报审表、延长工期报审表。",{"id":6,"name":31,"category":32,"favorite":33},"二建水利水电实务","建筑工程",0]