[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128594":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1128594,793,2,"多选题","（2017年）根据《小型水电站建设工程验收规程》（SL 168-2012），水电站单位工程完工验收后，在项目法人颁发合同工程完工证书前，施工验收工作包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程移交运行管理单位",false,{"key":16,"text":17,"correct":18},"B","验收遗留问题处理",true,{"key":20,"text":21,"correct":14},"C","提交工程质量保修书",{"key":23,"text":24,"correct":14},"D","提交竣工资料",{"key":26,"text":27,"correct":18},"E","施工场地清理","BE","考点:合同工程完工验收的基本要求。合同工程完工验收应包括以下主要内容：（1）检查合同范围内工程项目和工作完成情况；（2）检查施工现场清理情况；（3）检查已投入使用工程运行情况；（4）检查验收资料整理情况；（5）评定工程施工质量等级；（6）检查工程完工结算情况；（7）检查历次验收遗留问题处理情况；（8）对验收中发现的问题提出处理意见；（9）确定合同工程完工日期；（10）讨论并通过合同工程完工验收鉴定书。",{"id":6,"name":31,"category":32,"favorite":33},"二建水利水电实务","建筑工程",0]