[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128593":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1128593,793,2,"多选题","根据水利水电工程验收有关规定，下列关于大型拦河水闸工程验收的说法中正确的是()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","应进行蓄水验收",false,{"key":16,"text":17,"correct":18},"B","由竣工验收主持单位决定是否进行蓄水验收",true,{"key":20,"text":21,"correct":18},"C","应进行竣工验收技术鉴定",{"key":23,"text":24,"correct":14},"D","由竣工验收主持单位决定是否进行竣工验收技术鉴定",{"key":26,"text":27,"correct":14},"E","在建设项目全部完成后3个月内进行竣工验收","BC","大型拦河水闸工程验收的要求，(1)水库下闸蓄水前，应进行下闸蓄水验收。（A错误）；(5)拦河水闸工程可根据工程规模、重要性，由竣工验收主持单位决定是否组织蓄水(挡水）验收。（B正确），(2)大型水利工程在竣工技术预验收前，应按照有关规定进行竣工验收技术鉴定。中型水利工程，竣工验收主持单位可以根据需要决定是否进行竣工验收技术鉴定。（C正确，D错误）;根据《水利水电建设工程验收规程》SL223—2008,竣工验收应在工程建设项目全部完成并满足一定运行条件后1年内进行。",{"id":6,"name":31,"category":32,"favorite":33},"二建水利水电实务","建筑工程",0]