[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128590":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1128590,793,2,"多选题","根据《小型水电站建设工程验收规程》（SL168—2012），小水电站工程验收分为（）验收。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","分部工程",true,{"key":16,"text":17,"correct":14},"B","单位工程",{"key":19,"text":20,"correct":21},"C","单元工程",false,{"key":23,"text":24,"correct":14},"D","机组启动",{"key":26,"text":27,"correct":14},"E","竣工","ABDE","3小水电工程验收工作按验收主持单位可分为法人验收和政府验收。法人验收应包括分部工程验收、单位工程验收、合同工程完工验收及中间机组启动验收等；政府验收应包括阶段验收（含首末台机组启动验收）、专项验收、竣工验收等，验收主持单位可根据工程建设需要增设验收的类别和具体要求。",{"id":6,"name":31,"category":32,"favorite":33},"二建水利水电实务","建筑工程",0]