[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128564":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1128564,793,2,"多选题","（2017年）根据《关于鼓励和引导社会资本参与重大水利工程建设运营的实施意见》（发改农经[2015]488号），PPP项目中社会资本退出前应完成的工作包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","后评价",false,{"key":16,"text":17,"correct":18},"B","清产核资",true,{"key":20,"text":21,"correct":18},"C","落实项目资产处理方案",{"key":23,"text":24,"correct":18},"D","落实建设与运行后",{"key":26,"text":27,"correct":14},"E","绩效评价","BCD","考点:水利工程建设项目管理“三项”制度。政府有关部门应建立健全社会资本退出机制，在严格清产核资、落实项目资产处理和建设与运行后续方案的情况下，允许社会资本退出。",{"id":6,"name":31,"category":32,"favorite":33},"二建水利水电实务","建筑工程",0]