[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128561":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1128561,793,2,"多选题","（2019年）根据水利部《关于调整水利工程建设项目施工准备开工条件的通知》(水建管[2017]177号),项目施工准备开工应满足的条件包括（）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目可行性研究报告已经批准",true,{"key":16,"text":17,"correct":14},"B","环境影响评价文件已批准",{"key":19,"text":20,"correct":14},"C","年度投资计划已下达",{"key":22,"text":23,"correct":24},"D","初步设计报告已批复",false,{"key":26,"text":27,"correct":14},"E","建设资金已落实","ABCE","根据水利部《关于调整水利工程建设项目施工准备开工条件的通知》 (水建管[2017]177号) ，将水利工程建设项目施工准备开工条件调整为:项目可行性研究报告已经批准，环境影响评价文件等已经批准，年度投资计划已下达或建设资金已落实；项目法人即可开展施工准备，开工建设。?",{"id":6,"name":31,"category":32,"favorite":33},"二建水利水电实务","建筑工程",0]