[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128558":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1128558,793,2,"多选题","根据《水利工程设计变更管理暂行办法》（水规计[2012]93号），水利工程设计变更分为（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","一般设计变更",true,{"key":16,"text":17,"correct":18},"B","普通设计变更",false,{"key":20,"text":21,"correct":18},"C","较大设计变更",{"key":23,"text":24,"correct":14},"D","重大设计变更",{"key":26,"text":27,"correct":18},"E","特别重大设计变更","AD","2)水利工程设计变更分为重大设计变更和一般设计变更。",{"id":6,"name":31,"category":32,"favorite":33},"二建水利水电实务","建筑工程",0]