[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128557":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1128557,793,2,"多选题","水利水电工程施工准备阶段的主要工作内容包括()等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","办理土地使用权批准手续",false,{"key":16,"text":17,"correct":18},"B","施工现场的征地、拆迁",true,{"key":20,"text":21,"correct":18},"C","施工现场“四通一平”",{"key":23,"text":24,"correct":18},"D","招标设计",{"key":26,"text":27,"correct":14},"E","确定筹资方案","BCD","1.施工准备阶段的主要工作有：(1)开展征地、拆迁。实施施工用水、用电、通信、进场道路和场地平整等工程；(2)实施必需的生产、生活临时建筑工程；(3)实施经批准的应急工程、试验工程等专项工程；(4)组织招标设计、咨询、设备和物资采购等服务;(5)组织相关监理招标；(6)组织主体工程施工招标的准备工作等。",{"id":6,"name":31,"category":32,"favorite":33},"二建水利水电实务","建筑工程",0]