[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128504":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1128504,793,2,"多选题","土坝坝身控制测量包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","坝轴线测设",false,{"key":16,"text":17,"correct":18},"B","平面控制测量",true,{"key":20,"text":21,"correct":14},"C","坡脚线放样",{"key":23,"text":24,"correct":18},"D","高程控制测量",{"key":26,"text":27,"correct":14},"E","清基开挖线放样","BD","土石坝施工放样，坝轴线是土坝施工放样的主要依据，要进行土坝的细部放样，还必须进行坝身控制测量。坝身控制测量包括平面控制测量和高程控制测量。",{"id":6,"name":31,"category":32,"favorite":33},"二建水利水电实务","建筑工程",0]