[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128488":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1128488,793,1,"单选题","根据《水法》规定，在国家确定的重要江河、湖泊上建设水工程，在（）前，应取得流域管理机构签署的水工程的建设符合流域综合规划要求的规划同意书。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目建议书报请批准",false,{"key":16,"text":17,"correct":14},"B","可行性研究报告报请批准",{"key":19,"text":20,"correct":14},"C","初步设计报告报请批准",{"key":22,"text":23,"correct":24},"D","建设单位开工建设",true,"2020版教材P326 《水法》第十九条规定：“建设水工程，必须符合流域综合规划。在国家确定的重要 江河、湖泊和跨省、自治区、直辖市的江河、湖泊上建设水工程，未取得有关流域管理机 构签署的符合流域规划要求的规划同意书的，建设单位不得开工建设。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]