[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128476":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128476,793,1,"单选题","根据《水工碾压混凝土施工规范》SL 53-94，连续上升铺筑的碾压混凝土，层间允许间隔时间，应控制在（）以内。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初凝时间",true,{"key":16,"text":17,"correct":18},"B","终凝时间",false,{"key":20,"text":21,"correct":18},"C","45min",{"key":23,"text":24,"correct":18},"D","90min","2020版教材P360 4.5.6连续上升铺筑的碾压混凝土，层间允许间隔时间（系指下层混凝土拌合物拌合加水时起到上层混凝土碾压完毕为止），应控制在混凝土初凝时间以内。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]