[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128469":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1128469,793,1,"单选题","根据《水工建筑物地下开挖工程施工技术规范》(SDJ 212-83)，下列关于水利水电工程土石方开挖施工的说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","土石方明挖施工，未经安全技术论证和主管部门批准，严禁采用自下而上的开挖方式",false,{"key":16,"text":17,"correct":18},"B","大断面隧洞采用先拱后墙法施工时，拱脚线的最低点至下部开挖面的距离，不宜小于1.2m",true,{"key":20,"text":21,"correct":14},"C","洞口削坡应自上而下进行，严禁上下垂直作业",{"key":23,"text":24,"correct":14},"D","特大断面洞室采用先拱后墙法施工时，拱脚线的最低点至下部开挖面的距离不宜小于1.5m","2020版教材P357 当特大断面洞室设有拱座，采用先拱后墙法开挖时，应注意保护和加固拱座岩体。拱脚开挖应符合下列要求：1.拱脚下部开挖面至供脚最低点的距离不宜小于1.5m。2.拱混凝土衬砌强度不应低于设计强度的75%。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]