[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128467":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1128467,793,1,"单选题","水力发电工程的工程项目划分一般分为（）级。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","4",true,{"key":23,"text":24,"correct":14},"D","5","2020版教材P310 (1) 工程项目划分。工程开工申报及施工质量检查，一般按单位工程、分部工程、 分项工程、单元工程四级进行划分及工程开工申报。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]