[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128465":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128465,793,1,"单选题","根据《水利工程建设项目施工监理规范》，水利工程建设项目施工监理开工条件的控制中不包括（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","签发进场通知",true,{"key":16,"text":17,"correct":18},"B","签发开工通知",false,{"key":20,"text":21,"correct":18},"C","分部工程开工",{"key":23,"text":24,"correct":18},"D","单元工程开工","2020版教材P308 一、开工条件的控制包括签发开工通知、分部工程开工、单元工程开工、混凝土浇筑开仓。第一个单元工程在分部工程开工批准后开工，后续单元工程凭监理机构签认的上一单元工程施工质量合格文件方可开工。监理机构应对承包人报送的混凝土浇筑开仓报审表进行审核。符合开仓条件后，方可签发。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]