[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128441":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1128441,793,1,"单选题","根据《水利水电建设工程验收规程》(SL223-2008)的有关规定，单位工程完工并具备验收条件时，施工单位应向项目法人提出验收申请报告。项目法人应在收到验收申请报告之日()个工作日内决定是否同意进行验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",true,{"key":16,"text":17,"correct":18},"B","15",false,{"key":20,"text":21,"correct":18},"C","20",{"key":23,"text":24,"correct":18},"D","5","2020版教材P275 单位工程完工并具备验收条件时，施工单位应向项目法人提交验收申请报告。项目法人应在收到验收申请报告之日起10个工作日内决定是否同意进行验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]