[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128406":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1128406,793,1,"单选题","工程实施过程中，需对单位工程、主要分部工程、重要隐蔽单元工程和关键部位单元工程的项目划分进行调整时，项目法人应报送（）确认。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主管部门",false,{"key":16,"text":17,"correct":18},"B","质量监督单位",true,{"key":20,"text":21,"correct":14},"C","县级以上人民政府",{"key":23,"text":24,"correct":14},"D","流域机构","2020版教材P228 (3)工程实施过程中，需对单位工程、主要分部工程、重要隐蔽单元工程和关键部位单元工程的项目划分进行调整时，项目法人应重新报送工程质量监督机构确认。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]