[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128389":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1128389,793,1,"单选题","单元工程在施工单位自检合格的基础上，由( )进行终检验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计单位",false,{"key":16,"text":17,"correct":14},"B","项目法人",{"key":19,"text":20,"correct":21},"C","监理单位",true,{"key":23,"text":24,"correct":14},"D","质量监督部门","2020版教材P227 ②单元工程的检查验收，施工单位应按“三级检查制度”（班组初检、作业队复检、项目部终检）的原则进行自检，在自检合格的基础上，由监理单位进行终检验收。经监理单位同意，施工单位的自检工作分级层次可以适当简化。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]