[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128379":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1128379,793,1,"单选题","由项目法人负责组织有关单位制定处理方案并实施的质量事故是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","重大质量事故",false,{"key":16,"text":17,"correct":14},"B","较大质量事故",{"key":19,"text":20,"correct":21},"C","一般质量事故",true,{"key":23,"text":24,"correct":14},"D","特大质量事故","2020版教材P222 (1)一般质量事故，由项目法人负责组织有关单位制定处理方案并实施，报上级主管部门备案。(2)较大质量事故，由项目法人负责组织有关单位制定处理方案，经上级主管部门审定后实施，报省级水行政主管部门或流域备案。(3)重大质量事故，由项目法人负责组织有关单位提出处理方案，征得事故调查组意见后，报省级水行政主管部门或流域机构审定后实施。(4)特大质量事故，由项目法人负责组织有关单位提出处理方案，征得事故调查组意见后，报省级水行政主管部门或流域机构审定后实施，并报水利部备案。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]