[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1128338":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1128338,793,1,"单选题","某一级堤防工程施工过程中，承包人未通知监理机构及有关方面人员到现场验收，即将隐蔽部位覆盖，事后监理机构指示承包人采用钻孔探测进行检验，发现检查结果合格，由此增加的费用应由( )承担。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":14},"B","监理人",{"key":19,"text":20,"correct":21},"C","承包人",true,{"key":23,"text":24,"correct":14},"D","分包商","2020版教材P200 承包人覆盖工程隐蔽部位后，监理人对质量有疑问的，可要求承包人对已覆盖的部位进行钻孔探测或揭开重新检验，承包人应遵照执行，并在检验后重新覆盖恢复原状。经检验证明工程质量符合合同要求的，由发包人承担由此增加的费用和（或）工期延误，并支付承包人合理利润;.经检验证明工程质量不符合合同要求的，由此增加的费用和（或）工期延误由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"二建水利水电实务","建筑工程",0]